-Construction Plans are currently at 90% complete
-The Grading Permit was approved by the County
-The new playground has been ordered
-We will be completing the bid documents for the project over the next few weeks. Foothills anticipates going to bid sometime in February or March
The project website can be found here:
https://www.ifoothills.org/projects/#lakehurst-park